TY - JOUR
T1 - Storage site selection process in the North Sea for the ACT ACORN CCS Project
AU - Alcalde, Juan
AU - Bond, Clare Elizabeth
AU - James, Alan
AU - Robertson, Hazel
AU - Dumenil, Tim
AU - Pilbeam, David Christopher
AU - Heinemann, Niklas
AU - Haszeldine, R. Stuart
AU - Ghanbari, Saeed
AU - Mackay, Eric J.
AU - Faulkner, Daniel R.
AU - Allen, Michael J.
AU - Worden, Richard H.
PY - 2018
Y1 - 2018
N2 - The ACT ACORN is a CCS project funded by ERA-NET under the Horizon 2020
programme that aims to develop a protocol for a low cost, scalable full
chain CCS hub that will capture CO2 emissions from the St Fergus Gas
Terminal in North East Scotland and store the CO2 at an offshore storage
site under the North Sea. The project will build the case around one of
two potential storage sites; a pre-identified storage site Captain X
with CO2 storage planned in the Captain Sandstone, and a second site
('Site 2'). This work describes the methodology and process used in the
selection of Site 2 the methodology of which can be applied in future
CO2 storage site selection processes globally. For ACORN the initial
Basis of Design ensured that the screening and appraisal methodology was
suitable for the objectives of the project, that it should be low-cost
and operational by 2022. To ensure this, infrastructure in the form of
three pipelines (Goldeneye, WAGES and MGS pipelines) that connect the St
Fergus Gas Terminal to North Sea fields are planned to be reused, to
limit the total cost of implementation. A previously constructed
database (CO2Stored) of potential UK North Sea CO2 storage sites was
used as the baseline. The 579 storage sites in the database were mapped
and those sites lying out with 50km from the three target pipelines were
excluded. 113 sites complied with the Basis of Design requirements. Six
further criteria were then applied to screen the sites, further reducing
the number of suitable sites to 16: storage capacity >50MT, reservoir
porosity >10%, permeability >100mD, availability for operation by
2022 (in hydrocarbon fields), good seismic data coverage and well data
available. The remaining 16 sites were ranked according to six new
criteria: theoretical capacity, injectivity, development cost,
containment risk, storage efficiency and upside potential. These six
criteria enabled ranking of the sites in order of suitability as the
second storage site. The top six sites ranked were selected for a more
detailed due diligence, that included an analysis of 3D seismic over the
due diligence area, the reservoir properties (permeability, net-to-gross
ratio, porosity, etc.), well-log interpretations, geological and
engineering risks to containment and an indicative cost estimate. The
results of the due diligence process enabled the selection of 'East Mey'
as a suitable option for storage site 2, based on robust data sources.
The East Mey area has a significant potential storage resource and
injectivity, a proven caprock system, which serves a primary role for
several large oil and gas fields in the Central North Sea, and with
access to useful, confidence-building static and dynamic data from
hydrocarbon fields, which have produced from the target storage
formation. The Captain X and East Mey sites will now be characterised
and developed to allow full reservoir simulations of CO2 injection to
demonstrate their effectiveness as ACORNS from which a scalable,
full-chain CCS hub can be developed in the UK North Sea.
AB - The ACT ACORN is a CCS project funded by ERA-NET under the Horizon 2020
programme that aims to develop a protocol for a low cost, scalable full
chain CCS hub that will capture CO2 emissions from the St Fergus Gas
Terminal in North East Scotland and store the CO2 at an offshore storage
site under the North Sea. The project will build the case around one of
two potential storage sites; a pre-identified storage site Captain X
with CO2 storage planned in the Captain Sandstone, and a second site
('Site 2'). This work describes the methodology and process used in the
selection of Site 2 the methodology of which can be applied in future
CO2 storage site selection processes globally. For ACORN the initial
Basis of Design ensured that the screening and appraisal methodology was
suitable for the objectives of the project, that it should be low-cost
and operational by 2022. To ensure this, infrastructure in the form of
three pipelines (Goldeneye, WAGES and MGS pipelines) that connect the St
Fergus Gas Terminal to North Sea fields are planned to be reused, to
limit the total cost of implementation. A previously constructed
database (CO2Stored) of potential UK North Sea CO2 storage sites was
used as the baseline. The 579 storage sites in the database were mapped
and those sites lying out with 50km from the three target pipelines were
excluded. 113 sites complied with the Basis of Design requirements. Six
further criteria were then applied to screen the sites, further reducing
the number of suitable sites to 16: storage capacity >50MT, reservoir
porosity >10%, permeability >100mD, availability for operation by
2022 (in hydrocarbon fields), good seismic data coverage and well data
available. The remaining 16 sites were ranked according to six new
criteria: theoretical capacity, injectivity, development cost,
containment risk, storage efficiency and upside potential. These six
criteria enabled ranking of the sites in order of suitability as the
second storage site. The top six sites ranked were selected for a more
detailed due diligence, that included an analysis of 3D seismic over the
due diligence area, the reservoir properties (permeability, net-to-gross
ratio, porosity, etc.), well-log interpretations, geological and
engineering risks to containment and an indicative cost estimate. The
results of the due diligence process enabled the selection of 'East Mey'
as a suitable option for storage site 2, based on robust data sources.
The East Mey area has a significant potential storage resource and
injectivity, a proven caprock system, which serves a primary role for
several large oil and gas fields in the Central North Sea, and with
access to useful, confidence-building static and dynamic data from
hydrocarbon fields, which have produced from the target storage
formation. The Captain X and East Mey sites will now be characterised
and developed to allow full reservoir simulations of CO2 injection to
demonstrate their effectiveness as ACORNS from which a scalable,
full-chain CCS hub can be developed in the UK North Sea.
M3 - Conference article
SN - 1029-7006
VL - 20
JO - Geophysical Research Abstracts
JF - Geophysical Research Abstracts
M1 - 19050
T2 - European Geosciences Union<br/>General Assembly 2018
Y2 - 8 April 2018 through 13 April 2018
ER -